SAP C-ACTIVATE13 Cert Guide PDF 100% Cover Real Exam Questions
Pass C-ACTIVATE13 Exam - Real Questions & Answers
SAP Activate Project Manager Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books | Weighting |
|---|---|---|
| Transition Path "System Conversion" | Describe concepts, landscape overview and specifics in Workstreams related to “System Conversion” Transition Path. ACT100 (SAP S/4HANA 1809) | < 8% |
| Workstreams Overview | Describe concepts, artefact flows, accelerators, tools and roles for each Workstream within SAP Activate Methodology. ACT100 (SAP S/4HANA 1809) | > 12% |
| Agile Project Delivery | Describe how the project team prepares release and sprint plans, and the structure and key activities in each sprint. Discuss key techniques used in agile projects. ACT100 (SAP S/4HANA 1809) | > 12% |
| SAP Activate Overview | Define factors influencing SAP Activate, its purpose and place among other frameworks. ACT100 (SAP S/4HANA 1809) | > 12% |
| SAP Activate Elements | Provide an overview of content, tools and methodology elements of SAP Activate Solution Implementation Framework. ACT100 (SAP S/4HANA 1809) | > 12% |
| Agile Project Planning | Describe the agile project roles and responsibilities and the preparation of the project including the planning, estimation, user story mapping and construction of backlog. ACT100 (SAP S/4HANA 1809) | 8% - 12% |
| Transition Path "Selective Data Transition" | Describe concepts, landscape overview and specifics in Workstreams related to “Selective Data Transition” Transition Path. ACT100 (SAP S/4HANA 1809) | < 8% |
| Transition Path "New Implementation SAP S/4HANA On Premise" | Describe concepts, landscape overview and specifics in Workstreams related to implementing SAP S/4HANA On Premise. ACT100 (SAP S/4HANA 1809) | < 8% |
SAP Activate Project Manager Certification Exam Details:
| Reference Books | ACT100 (SAP S/4HANA 1809) ACT200 (SEE COURSE DETAIL) |
| Duration | 180 mins |
| Exam Price | $550 (USD) |
| Exam Name | SAP Certified Associate - SAP Activate Project Manager |
| Schedule Exam | SAP Training |
| Exam Code | C_ACTIVATE13 |
| Level | Associate |
| Passing Score | C_ACTIVATE13 - 65% |
| Sample Questions | SAP Activate Project Manager Certification Sample Questions |
NEW QUESTION 55
What is the primary purpose of the SAP Activate Methodology?
Please choose the correct answer.
Response:
- A. To provide the sequence of actions in the project
- B. To manage solution documentation
- C. To provide end-to-end Application Lifecycle Management
- D. To enable access to the SAP ecosystem
Answer: A
NEW QUESTION 56
Which end-to-end turn-key Application Lifecycle Management (ALM) solution can support you in managing requirements and software development for large, Agile projects?
Please choose the correct answer.
Response:
- A. Solution Manager Test Suite
- B. Focused Build
- C. Requirement Management
- D. Change Request Management
Answer: B
NEW QUESTION 57
What does the Side-by-Side Extensibility Option mean?
Please choose the correct answer.
Response:
- A. Extensibility based on the SAP Cloud Platform and published APls
- B. Transfer reporting to BW/4HANA
- C. Context-aware SAP S/4HANA extensions, focused on tight integration
- D. Have two SAP S/4HANA instances - one for standard code, and another for custom developments
Answer: A
NEW QUESTION 58
How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
Response:
- A. Register on SAP Service Marketplace
- B. Submit e-mail address via on-line form
- C. Join SAP S/4HANA group on SAP Community Network
- D. Send e-mail to SAP contact address
Answer: B
NEW QUESTION 59
What accelerator can help you document the Configuration Definition in the Explore phase?
Please choose the correct answer.
Response:
- A. Test Strategy
- B. Data Definition
- C. Backlog template
- D. Change Request template
Answer: C
NEW QUESTION 60
In which tools can the project team across the SAP Activate Methodology content including accelerators?
There are 2 correct answers to this question.
Response:
- A. SAP Jam
- B. SAP Community Network
- C. Roadmap Viewer
- D. SAP Service Marketplace
Answer: A,C
NEW QUESTION 61
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
Please choose the correct answer.
Response:
- A. Prepare
- B. Deploy
- C. Explore
- D. Realize
Answer: B
NEW QUESTION 62
Which key deliverable includes the development of RICEFW objects?
Please choose the correct answer.
Response:
- A. Sprint Execution
- B. Custom Extensions Management
- C. Development Build
- D. Enhancement Delivery
Answer: D
NEW QUESTION 63
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
Please choose the correct answer.
Response:
- A. User Stories are in a Ready state for NO more than the first three Sprints.
- B. Project scope and planning are completed and final.
- C. Go-Live scope is fixed on the first of January the following year.
- D. Timelines of the Sprint may differ due to the workload.
Answer: A
NEW QUESTION 64
What do you do during Sprint Execution?
Please choose the correct answer.
Response:
- A. Hold a retrospective at the end of each week
- B. Present status of selected user stories in the sprint scope on a scrumboard
- C. End a sprint when the sprint backlog items are all complete
- D. Measure the sprint progress with a percentage complete report
Answer: D
NEW QUESTION 65
According to the Definition of Done, which activity must be completed for each sprint?
Please choose the correct answer.
Response:
- A. End user training must be delivered
- B. Functionality must be released to the business
- C. The Solution must be built and configured in the development system (DEV)
- D. Functionality must be tested in the Quality system (QAS)
Answer: C
NEW QUESTION 66
Which of the following is not correct about Fit/Gap Analysis?
There are 2 correct answers to this question.
Response:
- A. Validate pre-activate and pre-assembled solution in the development system.
- B. Minimize the needs for rework during realization.
- C. Prioritize delta requirement and gaps.
- D. Drive towards adopting customers processes.
Answer: A,D
NEW QUESTION 67
Where can you find Project Library Accelerators?
Please choose the correct answer.
Response:
- A. Fully Activated Appliance
- B. SAP Best Practices Explorer
- C. SAP Roadmap Viewer
- D. SAP Cloud Appliance Library
Answer: C
NEW QUESTION 68
What is the best target deployment option of SAP S/4HANA for the "System Conversion" transition path?
Please choose the correct answer.
Response:
- A. SAP S/4HANA Cloud
- B. SAP S/4HANA
- C. Hybrid of SAP S/4HANA Cloud and SAP S/4HANA
- D. SAP C/4HANA
Answer: C
NEW QUESTION 69
What Solution Operations Framework can customers use to create a joint Business and IT organization, that will secure transparency and efficiency of SAP implementation, innovation, operation, and quality of business processes and systems?
Please choose the correct answer.
Response:
- A. Customer Center of Expertise
- B. Business Transformation Management Methodology
- C. SAP Operations Control Center
- D. SAP Activate
Answer: A
NEW QUESTION 70
What is the difference between the "System Conversion and the "New Implementation of SAP S/4HANA" transition paths?
There are 2 correct answers to this question.
Response:
- A. In the Realize phase, custom code is adjusted rather than developed for System Conversion.
- B. In the Realize phase, data is converted and NOT migrated for System Conversion.
- C. SSCUls are used in System Conversion for configuring SAP S/4HANA through the Manage Your Solution app.
- D. There are different upgrade cycles.
Answer: A,B
NEW QUESTION 71
What is the correct order of the SAP Activate Methodology phases?
Please choose the correct answer.
Response:
- A. Plan -> Design -> Build -> Operate
- B. Plan -> Build -> Run -> Sustain
- C. Prepare -> Discover -> Explore -> Realize -> Deploy -> Run
- D. Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
Answer: D
NEW QUESTION 72
What is a benefit of using Guided Configuration instead of the Implementation Guide?
Please choose the correct answer.
Response:
- A. It ensures SAP updates do NOT conflict with customer configurations
- B. It ensures configuration is done using SAP Solution Manager
- C. It eliminates the need for Content Lifecycle Management
- D. It eliminates the need to generate transport requests for configuration settings
Answer: A
NEW QUESTION 73
Which of the following belong to the Application Design and Configuration work stream for SAP S/4HANA Cloud in the Explore phase?
There are 2 correct answers to this question.
Response:
- A. Integration prerequisites confirmation
- B. Configuration definition
- C. Kick-off workshop
- D. Fit-to-standard workshop
Answer: B,D
NEW QUESTION 74
Which artifacts in the Testing work stream are created within the Realize phase for the New Implementation of SAP S/4HANA Cloud" transition path?
There are 2 correct answers to this question.
Response:
- A. Functional Test Scenarios
- B. Reporting Functional Specifications
- C. User Acceptance Test - Plan
- D. Functional Specifications
Answer: A,C
NEW QUESTION 75
What technique helps a Scrum Team to prioritize a large, flat Backlog?
Please choose the correct answer.
Response:
- A. Planning Poker
- B. Fit/Gap Analysis
- C. Retrospective
- D. User Story Mapping
Answer: D
NEW QUESTION 76
What is the final activity in the Realize phase of a new implementation of SAP S/4HANA cloud edition?
Please choose the correct answer.
Response:
- A. Data migration
- B. Solution validation
- C. Readiness check
- D. End-to-End walkthrough
Answer: D
NEW QUESTION 77
What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud?
Please choose the correct answer.
Response:
- A. SAP Transformation Navigator
- B. SAP Roadmap Viewer
- C. SAP Support Marketplace
- D. Implementation portal for SAP S/4HANA Cloud
Answer: D
NEW QUESTION 78
Which activity is part of the SAP Activate Methodology for a new implementation of SAP S/4HANA on- premise edition but NOT of the cloud edition?
Please choose the correct answer.
Response:
- A. Technical System Test
- B. End-to-End Integration Test
- C. Unit Test
- D. User Acceptance Test
Answer: A
NEW QUESTION 79
In Which phase does the Transition to Operations work stream start?
Please choose the correct answer.
Response:
- A. Prepare
- B. Realize
- C. Deploy
- D. Explore
Answer: B