Less time for high efficiency
As everyone knows, preparing for an exam is a time-consuming as well as energy-consuming course, however, as it is worldly renowned well begun, half done, if you choose to use our 070-178 test prep materials, you can save most of your time as well as energy since we can assure that you can pass the IT exam and get the IT certification with a minimum of time and effort. The contents in our Microsoft 070-178 exam resources are all quintessence for the IT exam, which covers all of the key points and the latest types of examination questions and you can find nothing redundant in our 070-178 test prep materials. Therefore, you can finish practicing all of the essence of IT exam only after 20 to 30 hours. After practicing all of the contents in our 070-178 exam resources it is no denying that you can pass the IT exam as well as get the IT certification as easy as rolling off a log.
Free renewal for a year
Once you buy our 070-178 test prep materials, during the whole year, as soon as we have compiled a new version of the exam study materials, our company will send the latest one to you for free. Our top IT experts are always keep an eye on even the slightest change in the IT field, and we will compile every new important point immediately to our Microsoft 070-178 exam resources, so we can assure that you won't miss any key points for the IT exam. And please think about this, as I just mentioned, in the matter of fact, you can pass the exam with the help of our exam study materials only after practice for 20 to 30 hours, which means it is highly possible that you can still receive the new 070-178 test prep materials from us after you have passed the exam if you are willing, so you will have access to learn more about the important knowledge of the IT industry or you can pursue wonderful 070-178 pass score, it will be a good way for you to broaden your horizons as well as improve your skills. You can see it is clear that there are only benefits for you to buy our Microsoft 070-178 exam resources, so why not have a try?
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
There is no doubt that there is a variety of Microsoft 070-178 exam resources in the internet for the IT exam, and we know the more choices equal to more trouble, so we really want to introduce the best one to you and let you make a wise decision. It is said that a good beginning makes for a good ending. Therefore it goes naturally that choosing the right study materials is a crucial task for passing exam with good 070-178 pass score. We are so glad to know that you have paid attention to us and we really appreciate that, we will do our utmost to help you to pass the IT exam as well as get the IT certification. Owing to the high quality and favorable price of our 070-178 test prep materials, our company has become the leader in this field for many years. There is really a long list to say about the strong points of our 070-178 exam resources, including less time for high efficiency, free renewal for a year, to name but a few.
Microsoft 070-178 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: Closing Projects | - Project closure activities
|
| Topic 2: Planning Projects | - Resource planning and allocation
|
| Topic 3: Monitoring and Controlling Projects | - Managing changes
|
| Topic 4: Initiating Projects | - Defining project scope and objectives
|
| Topic 5: Executing Projects | - Project execution tracking in Microsoft Project
|
Microsoft Project 2010, Managing Projects Sample Questions:
1. The project you manage has only part-time resources. The part-time resources work four hours a day from Wednesday through Saturday. You need to create a new calendar and set the calendar as the default for your project. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A) Set the calendar type to part-time for all tasks.
B) Select the part-time calendar from the Project Information window.
C) Change the Calendar type in the Project Options dialog box.
D) On the Project tab, Select Change Working Time, and then click Create New Calendar.
E) Select the part-time calendar from the Change Working Time window.
2. You have a Project 2010 schedule that contains the following tasks: Inactive tasks Manually scheduled tasks Manually scheduled summary tasks Tasks that contain strikethrough font You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are created. What should you do?
A) Change all inactive tasks to active tasks.
B) Change all tasks that contain strikethrough font to tasks that include normal font.
C) Change all manually scheduled summary tasks to automatic scheduling.
D) Change all manually scheduled tasks to automatic scheduling.
3. You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task. What should you do?
A) Create a custom field and capture travel costs at the project level.
B) Use a cost type resource.
C) Use a work type resource.
D) Use a budget resource.
4. You attempt to print the task table and Gantt chart horizontally. However, the task names do not appear on each printed page. You need to ensure that the task names are printed on each page.
What should you do?
A) Modify the settings in the Page Setup dialog box.
B) Modify the settings in the Field Settings dialog box of the Task Name column.
C) Select the Task Name column and click Print.
D) Select the Task Name column and click Add to Timeline.
E) Modify the settings in the Column Settings dialog box of the Task Name column.
5. You need to set the default constraint type for all new tasks to As Late As Possible. What should you do?
A) In the Project Information window, from the Schedule From drop-down list box, select Project Finish Date.
B) Select all tasks, and then set the constraint type to As Late As Possible.
C) Select all tasks, and then click Layout.
D) In the Options dialog box, enable the New Tasks are effort driven check box.
Solutions:
| Question # 1 Answer: B,D | Question # 2 Answer: A | Question # 3 Answer: C | Question # 4 Answer: A | Question # 5 Answer: A |