CompTIA PK0-400 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Monitoring and Control | 16% | - Issue resolution and escalation - Risk identification and mitigation - Performance tracking and reporting - Change control process |
| Project Management Foundations | 27% | - Project governance and methodologies - Roles, responsibilities, and organizational structures - Project characteristics and constraints - Stakeholder identification and engagement |
| Tools and Documentation | 8% | - Project management software and tools - Documentation standards and archiving - Communication tools and reporting formats |
| Planning and Execution | 24% | - Team leadership and resource management - Cost estimation and budgeting - Scope management and work breakdown structure - Schedule development and resource allocation - Quality assurance and control |
| Project Life Cycle Phases | 25% | - Planning phase scope, schedule, and cost estimation - Monitoring and controlling progress - Initiation phase activities and deliverables - Execution phase management and communication - Closure phase activities and documentation |
The CompTIA PK0-400 Exam: What to Know
Yes:
Build your knowledge base with official training, then go over the 96 practice questions for the CompTIA Project+ — that combination is the actual plan.
No formal prerequisites; recommended 6–12 months of hands-on project management experience Rules on eligibility change occasionally, so confirm the current requirements on the official page (official PK0-400 exam page) before you pay the fee.
90 minutes for Up to 95 questions. Adapt to the clock now: the GuideTorrent SOFT and APP versions let you control test time and track scores, so the real PK0-400 exam feels like a rehearsal you've already done.
Delivery: payment triggers an automatic email within a minute — download immediately, install without limits, and if nothing arrives within 2 hours our round-the-clock support helps (check spam first). Refund: unlike vendors with slow, cumbersome processes, we keep it clear — take the corresponding PK0-400 exam within 60 days of purchase, and if you fail, send a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam; the full refund is processed within 7 days. Excluded: exams within 3 days of purchase, candidate names that don't match the payer, and free or expired products. Or exchange for two equal-value products free.
Yes — three different free CompTIA Project+ demos are available to download. Do the demo test first to inspect the value, then decide. Purchases include 365 days of free updates, renewable at 50% off.
The CompTIA Project+ blueprint covers 5 domains — including Planning and Execution (24%), Project Life Cycle Phases (25%), Project Management Foundations (27%). Weightings point you to the heavy hitters; schedule your review accordingly. The complete outline above lists every subtopic.
Registration goes through the vendor's official channels:
The CompTIA Project+ is delivered In-person at Pearson VUE test centers or online remotely proctored — select whichever suits you when booking.
$390 USD per attempt, with 710 (scale 100-900) as the passing score. Since a failed attempt bills again, rehearse with the 96 practice questions from GuideTorrent until your tracked scores clear the mark consistently.
The CompTIA Project+ is CompTIA's official exam for the CompTIA Project+ credential (Professional level). Before anything else, verify the exam code and name match what you need — then build a plan around the official objectives. Related credentials include CompTIA Project+ PK0-005.
CompTIA Project+ Sample Questions:
Which of the following describes a burn rate?
- A. The rate at which the project budget is used.
- B. The rate at which project documents are disposed.
- C. The rate at which the timeline increases.
- D. The rate at which project personnel leave the project.
Correct Answer: A 🗳️
A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?
- A. RFI
- B. RFP
- C. RFO
- D. RFQ
Correct Answer: B 🗳️
The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
- A. Total project cost
- B. Cost baseline
- C. Cost variance report
- D. Burn rate
Correct Answer: B 🗳️
An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called:
- A. an MOU.
- B. an RFP.
- C. an SLA.
- D. an NDA.
Correct Answer: D 🗳️
A project manager is creating the WBS.
In which of the following phases is the project?
- A. Closing
- B. Execution
- C. Initiation
- D. Planning